banner

Blog

Oct 24, 2024

Navigating battery energy storage augmentation

Augmentation planning should consider permitting; potential impacts to civil, structural, electrical, supervisory, control and data acquisition; fire protection designs; and constructability.

As renewable energy sources continue to dramatically influence the electric grid, energy storage is playing a pivotal role in achieving grid resiliency. Though there are many available energy storage technologies, lithium-ion batteries are the most common energy storage technology. These battery energy storage systems (BESS) supply reliable power to the grid during times when renewable energy sources cannot, such as when the wind is not blowing or sun is not shining, and provide many auxiliary benefits.

One key design consideration for batteries is that they degrade over time. This means the amount of energy a battery can store is at its maximum on the first day of deployment and will steadily diminish until its end of life. To maintain facility capacity, more energy storage needs to be installed through a process called augmentation. Augmentation may also increase the site’s capacity and gives facility owners and operators enhanced functionality. Whether installing a new facility or expanding existing systems, the augmentation process requires careful upfront planning.

Before breaking ground on any battery energy storage system (BESS) project, preparing for future augmentation efforts is essential. Augmentation planning should consider permitting; potential impacts to civil, structural, electrical, supervisory, control and data acquisition; fire protection designs; and constructability. By implementing an augmentation plan upfront, owners can minimize potential delays and unforeseen costs when augmentation needs to occur.

A critical component of augmentation planning is the planned integration of future equipment with the initially installed equipment and infrastructure. The factors that must be considered are numerous and range from the more obvious—accounting for additional auxiliary power in electrical distribution equipment, for example—to others that are more knowledge-intensive, such as considering system voltages to balance state of charge while dispatching batteries with different states of health.

Close collaboration with the facility owner, BESS integrator or engineer, and battery original equipment manufacturer is crucial to assess compatibility and establish integration plans and technology selection.

The first branch reached in the planning decision tree is the choice between alternating-current (AC) or direct-current (DC) augmentation. AC augmentation consists of adding more inverters with dedicated batteries. DC augmentation adds battery modules to existing inverters. AC augmentation is conceptually simpler due to reduced interfaces with existing equipment. AC augmentation also increases the total inverter power output, either increasing the facility rating or providing increased inverter redundancy if designed with excess battery output. DC augmentation directly addresses the effects of battery degradation by adding only battery capacity. The two augmentation options offer unique advantages and challenges:

Advantages

Challenges

Advantages

Challenges

Once the approach to augmentation has been selected, it’s essential to evaluate the battery and inverter equipment to satisfy beginning-of-life and end-of-life battery energy criteria. System sizing and selection must carefully consider battery life span, depth of discharge and cycles per year. Additionally, impact of ambient conditions, number of augmentations and many other factors need to be thought through.

Site layouts need to include adequate space for initial and future equipment, while also considering all regulatory and code requirements, construction sequencing, and operations and maintenance needs during all phases of the facility operation.

Navigating the choppy waters of BESS augmentation demands an experienced team with a thorough understanding of design, construction and technology integration. Facility owners should also make certain that internal objectives and priorities are well understood, so that the optimal approach can be selected for a BESS project.

As the grid evolves and grows, and the march toward decarbonization increases with higher renewable energy utilization, BESS systems provide a critical backstop and improve energy security for the grid. BESS augmentation is and will continue to be a crucial aspect of BESS project planning, making it an essential component of the modern grid. By embracing innovation and adopting strategic planning approaches, owners can stay ahead of the curve and drive meaningful improvements in operations and services.

Jeff Danley, Associate Technology and Innovation Consultant at Burns & McDonnell, suggests several solutions generative AI could have within the construction industry.

As climate change is linked with biodiversity depletion, fostering biodiverse landscapes during construction can create benefits beyond the immediate surroundings of the project.

Burns & McDonnell breaks down three ways computer vision can effectively assist workers on the job site, from project progress to safety measures.

Burns & McDonnell breaks down the state of battery energy storage today, from pricing concerns to alternative solutions.

Zachary Wassenberg of Burns & McDonnell breaks down three applications for digital knowledge networks: training, libraries, and instructions.

Traditional sports and entertainment venues are fading as teams and entertainment entities strive to move toward more diversified entertainment districts.

When value engineering is referenced in our industry, our minds may immediately go to a process that reduces project cost by slashing scope or decreasing the quality of materials used. However, that is not necessarily what the definition should be.

There are several possibilities when it comes to reconfiguring or adjusting a space to maintain the health and safety of workers, from reorganizing spaces to enable social distancing measures to full teardown and reconstruction of a plant.

The short story is official design guidelines are slow to be developed and made into law.

First, most important and most complex: Create an extensive safety plan for your facilities and job sites that protects both the personnel onsite and the end users of your product.

To distinguish their life sciences campuses, developers are partnering with architectural and design firms to reimagine life sciences facilities as vibrant, welcoming destinations. By emphasizing four key elements—wellness, collaboration, biophilic design, and community integration—they are setting their properties apart.

A recently opened multifamily property in Lawrence, Mass., is an adaptive reuse of an 1840s-era mill building. Stone Mill Lofts is one of the first all-electric mixed-income multifamily properties in Massachusetts. The all-electric building meets ambitious modern energy codes and stringent National Park Service historic preservation guidelines.

AEC Giants with multifamily practices report that the sector has been struggling over the past year, despite the high demand for housing, especially affordable products.

In Newark, N.J., the New Jersey Performing Arts Center (NJPAC) has broken grown on the three-year, $336 million redevelopment of its 12-acre campus. The project will provide downtown Newark 350 mixed-income residential units, along with shops, restaurants, outdoor gathering spaces, and an education and community center with professional rehearsal spaces.

AdvantagesChallengesAdvantagesChallenges
SHARE